     Construction Guide
  
 

Application Prompt
Construction Procedures

Method of powder spreading: Base plane cleaning → Base plane amendment → Base plane moisturizing → Layer addition → Node treatment → Dry powder spreading with screen

Method of knife coating: Base plane cleaning → Base plane amendment → Base plane moisturizing → Layer addition → Node treatment → Primer coating → Surface coating

The application of all PS products must be subject to the instructions of the manufacturer’s representative or experienced technicians. Or, follow the Manufacturer’s Construction Manual for construction.
The construction of PS can not be done in rainy days or at the temperature of 5℃ below.
When the ambient temperature exceeds 20℃, the maintenance must last for 48 hours.。
24-72 hours after concrete pouring is the best time period of construction; for the newly-poured concrete is still moist, only a little water is to be sprayed on the base plane as required. In the sunshine time at high temperature in summer, it is suggested to construct in the morning, in the evening or at night to prevent the coating from drying too fast, which will lead to surface wrinkle and cracking and impact the penetration.
When the ambient temperature exceeds 20℃, the maintenance must last for 48 hours.

Precautions, Health and Safety
For PS is an alkali sustenance (as same as cement), please pay attention to the contact with eyes, the respiratory tract and the skin at application. It is required to wear the protective glasses, the anti-dust mask and gloves in construction.
If the material gets into eyes carelessly, please wash with clear water in time; if the symptom is not bettered, please see the doctor in time.

Tool Preparation
a、Cleaning tools: Hammer, chisel, shovel, wire brush, broom, rag, sprayer and gloves etc.
b、Mixing tools: Mixing bucket, distributing bucket, water bucket, mixer and meter etc.
c、Construction tools: Scraper, special brush, trowel and pallet.
d、Powder spreading tools: Special screen, sprayer, rubber gloves, gauze mask and other protective articles.

Reference Dosages of Materials

Construction Thickness(mm)

1.0

1.5

Reference Dosage(kg/m2)

1.5-1.8

2.0-2.3

  Friendly link:

意大利商协/工程协会(中文) 美国屋面工程协会 中国防水协会 中国建筑防水协会 中国防水网   陕西防水网
意大利商协/工程协会(英文) 中国建筑防水网   中国建材网   福建防水网       山西防水网   浙江防水网  辽宁防水网

All rights reserved face to face page Dalian Pnata High-efficient Building Materials Co., Ltd.  Contact us
Dalian Xinnet Science and technology - providing the technology hold out
《PRC telecommunication and information service business manage licence》Serial number:LiaoICPbei05002145Number